UPDATE: Milling is scheduled on Main Street (from N. Gaston Ave to Haynes Street) on Friday, November 15. Paving and striping is planned on Monday, November 18. Working hours will be from 9 am to 5 pm. Detours will be set up on both days.
PSE&G and contractor crews will continue working on the gas pipe replacement project.
Tuesday, November 12 to Friday, November 15
NOTE: Crews will not be working on Monday, November 11, in observance of Veterans Day.
- Crews will be connecting service lines and scheduling appointments on North Cadillac Dr and Catalina Dr
- On November 14 and 15 (TENTATIVE DATES), PSE&G may start milling and paving Main Street (from N Gaston Ave to Haynes Street), in the westbound lanes. This restoration work will occur during daytime hours. Police will guide traffic and place detour signs.
View the interactive map to see current work locations.
Questions
Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.