PSE&G gas construction update: week of January 27

Posted on January 24, 2025


PSE&G gas construction weekly update

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and “no parking” signs in sections of Main Street. Pedestrian access to all businesses will be maintained.

Monday, January 27

PSE&G crews will finish drilling test holes on Main Street.

  • Work Hours: 9 am to 2 pm (8 am setup)
  • Traffic Plan: Lane shift in traffic
  • Crews are also digging pits (in scattered locations), from 7 am to 3 pm

Tuesday, January 28 to Friday, January 31

PSE&G crews will install a gas main on Main Street.

  • Work Hours: 8 pm to 5 am (the NJ Department of Transportation approved closure from 7 pm to 6 am)
  • Work Area: Main Street, from Bridge Street to Giardina Walk
  • Traffic Plan: Detour off Main Street, at Mountain Avenue and Bridge Street
  • Crews are also digging pits (in scattered locations), from 7 am to 3 pm

Information session

PSE&G met with the Downtown Somerville Alliance and local business owners in December to explain the Main Street project.

Questions

Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.