PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and “no parking” signs in sections of Main Street. Pedestrian access to all businesses will be maintained.
Monday, February 10 to Friday, February 14
The overnight crew will NOT work on Main Street this week due to the weather forecast. Crews will work in scattered locations, from 7 am to 3 pm, to tie-in piping to the gas system.