PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting.
Monday, August 26 to Friday, August 30
Crews will be working on:
- Fieldstone Ave, installing main and connecting services between N Gaston Ave and Schoolhouse Ln
- Cleveland St, installing main between Union Ave and Halsey St. Continuing onto Halsey St and Eastern States Pkwy
- Also, scheduling appointments on Putnam St, Madison St and N Richards Ave
Note: Crews will not work on S. Adamsville Road on Saturday, August 31. They are expected to resume working on Saturday, September 7.
View the interactive map showing current work locations.
Questions
Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.