December 20: NJ American Water is aware of taste and odor issues and will continue flushing the water system. We are anticipating 1 to 2 inches of snow tonight into Saturday morning. Black ice is possible. Residents have 12 daylight hours to clear snow from sidewalks once the precipitation has ended.

Street paving for gas pipeline work

In September 2023, PSE&G started repaving streets after performing upgrades to the gas pipes under the roadways.

Timeline

  • Phase 1 of the paving project was completed in October
  • The plates on Main Street are expected to be removed by Friday, November 17
  • The work near the hospital is ongoing
  • PSE&G will continue working on service lines in January 2024
  • Final paving will start after the service lines are installed

Work details

  • Work hours are from 7 am to 6 pm
  • Work may be rescheduled if there are poor weather conditions
  • Residents can access roads during milling (surface) operations
  • Roads have restricted access on the dates scheduled for paving
  • No Parking signs will be posted 24 hours before work begins
  • There are no changes to the garbage and recycling pickup schedule

Phase 1 Schedule

Street Milling date Paving date
Walnut St (from S Cadillac Dr to E Spring St) September 28 October 3
S Cadillac Dr (from Center Pl to Walnut St, plus the intersection at Michael Ln) September 27 October 2-3
Michael Ln (from S Caddilac Dr to Everit Dr) September 27 October 2
Everit Dr (from Michael Ln to Center Pl) September 27 October 2
Fleetwood Dr (from Everit Dr to N Caddilac Dr) September 27 October 2
Riviera Dr (from Fleetwood Dr to E Caddilac Dr) September 27 October 2
Imperial Dr (from Fleetwood Dr to Seville Dr) September 28 October 2
Seville Dr (from Imperial Dr to Center Pl) September 27 October 3
Center Pl (from Seville Dr to S Caddilac Dr) September 28 October 3
Demond Pl (from Sycamore St to N Gaston Ave) October 2 October 4
Sycamore St (from E Spring St to William Ave) September 28 October 3
E Spring St (from Grove St to N Bridge St) October 2 October 4
W Spring St (from N Bridge St to Davenport St and Davenport St to Mercer St) October 2-3 October 4
E High St (the intersection at Mechanic St) October 4 October 9
Mechanic St (from E High St to E Main Ave) October 3 October 9
Park Ave (from E High St to E Main Ave) October 4 October 11
2nd St (from Hamilton St to S Bridge St) October 4 October 11
3rd St (from Hamilton St to S Bridge St) October 5 October 12
Center St (from Southside Ave to 2nd St) October 5 October 12
Southside Ave (from Center St to S Bridge St) October 6 October 12
E Young St (from Grove St to the end and Grove St to N Bridge St) October 9 October 16
N Gaston Ave (from William St to Route 22) October 10-11 October 17-18
Grove St (from William St to Route 22) October 6, 9-12 October 16

Contact

Mike Halperin
(908) 725-2300
ext. 1958

Gas Construction Customer Hotline