December 20: NJ American Water is aware of taste and odor issues and will continue flushing the water system. We are anticipating 1 to 2 inches of snow tonight into Saturday morning. Black ice is possible. Residents have 12 daylight hours to clear snow from sidewalks once the precipitation has ended.

PSE&G gas construction update: week of May 28

Posted on May 23, 2024


PSE&G map

PSE&G and contractor crews will continue working on the gas pipe replacement project. All work is weather permitting. Note: Crews will not work on Monday, May 27 in observance of the Memorial Day holiday.

This Week

Friday, May 24

PSE&G contractor crews will start striping the recently paved roads on Friday, May 24. Work will continue into early next week.

Next Week

Codington Pl

Tuesday May 28

  • Gas main installation between Main St and E. High St
  • Work hours: 7 am to 4 pm

N. Auten Ave

Tuesday, May 28 to Friday, May 31

  • Saw cutting and gas main installation from Main St to Rt 28
  • Work hours: 7 am to 4 pm

N. Gaston Ave

Wednesday, May 29 to Friday, May 31

  • Connecting services between Union Ave and Main St
  • Work hours: 9 am to 2:30 pm
  • Traffic control will include lane shifts and flagging (one lane of travel)

Questions

Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.

Close window