December 20: NJ American Water is aware of taste and odor issues and will continue flushing the water system. We are anticipating 1 to 2 inches of snow tonight into Saturday morning. Black ice is possible. Residents have 12 daylight hours to clear snow from sidewalks once the precipitation has ended.

PSE&G gas construction update: week of June 17

Posted on June 14, 2024


PSE&G June 17 map

PSE&G and contractor crews will continue working on the gas pipe replacement project.

Monday, June 17 to Friday, June 21

All work is weather permitting.

  • Rehill Ave: Installing a main between Union Ave and Fairmount Ave
  • Putnam St: Working between N Clark Ave and Post St (after Rehill Ave work is completed)
  • Codington Pl: Connecting services between Main St and E High St

Questions

Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.