PSE&G and contractor crews will continue working on the gas pipe replacement project.
Monday, July 22 to Friday, July 26
All work is weather permitting.
- Installing main on Somer Dr, between N. Gaston Ave and Fieldstone Dr
- Continuing onto Nagle Dr and Schoolhouse Ln
- Working on tie-in pits on Codington Pl, along multiple intersections (Monday)
- Installing gas main on Kirby Ave, between Haynes St and Van Doren Ave (Monday and Tuesday)
- Working on tie-in pits at Grove St and William St (Tuesday and Wednesday)
- Installing main on N. Richards Ave, between E. Main St and Hope St (Wednesday to Friday)
View the interactive map showing current work locations.
Questions
Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.