Borough Hall is closed on December 24 and 25 for the Christmas holiday. NJ American Water is aware of taste and odor issues. There are currently no drinking water advisories in place.

PSE&G gas construction update: November 20

Posted on November 20, 2023


PSE&G map week of November 20

Monday, November 20 to Wednesday, November 22

  • E. Cliff St (between Culver St and N. Gaston Ave): Installing main and connecting services
  • Culver St (between Bartine St and E. Cliff St): Installing main and connecting services
  • Additional Locations: PSEG will notify Somerville Police as the week progresses
  • We do not expect crews to work on November 23 and 24 due to the Thanksgiving holiday

About this project

PSE&G is working in Somerville to replace gas mains and services. This work is Phase 1 of a 10-12 month gas construction project. All crews will first finish installing new mains and then proceed to connect service lines.

Expect an increase in traffic, loud noise, and presence of heavy equipment and machinery in these areas. All work is pending weather and availability of materials.

Garbage collection

Plan for an earlier pickup while roads are under construction. Please put trash out the night before collection.

Questions and concerns

Contact the Gas Construction Customer Hotline at 1-833-661-6400 or gasworks@pseg.com.

Close window