Monday, November 20 to Wednesday, November 22
- E. Cliff St (between Culver St and N. Gaston Ave): Installing main and connecting services
- Culver St (between Bartine St and E. Cliff St): Installing main and connecting services
- Additional Locations: PSEG will notify Somerville Police as the week progresses
- We do not expect crews to work on November 23 and 24 due to the Thanksgiving holiday
About this project
PSE&G is working in Somerville to replace gas mains and services. This work is Phase 1 of a 10-12 month gas construction project. All crews will first finish installing new mains and then proceed to connect service lines.
Expect an increase in traffic, loud noise, and presence of heavy equipment and machinery in these areas. All work is pending weather and availability of materials.
Garbage collection
Plan for an earlier pickup while roads are under construction. Please put trash out the night before collection.
Questions and concerns
Contact the Gas Construction Customer Hotline at 1-833-661-6400 or gasworks@pseg.com.