December 20: NJ American Water is aware of taste and odor issues and will continue flushing the water system. We are anticipating 1 to 2 inches of snow tonight into Saturday morning. Black ice is possible. Residents have 12 daylight hours to clear snow from sidewalks once the precipitation has ended.

PSE&G gas construction update: May 6 week

Posted on May 3, 2024


PSE&G map

Plan for road closures and detours, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting.

N. Gaston Avenue

Monday, May 6 to Friday, May 10

  • Crews will be connecting services between Union Ave and Main St.
  • Work hours are from 9 am to 2 pm
  • Traffic control will include lane shifts and flagging (one lane of travel)

Codington Place

Tentative (dates to be confirmed)

  • Work on this street is tentatively planned
  • Crews will install a main between E. High St and Main St.
  • Work hours are from 9 am to 2 pm
  • This work will require a road closure

Questions

Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.