Plan for detours on Main Street, from N. Gaston Ave to Haynes St, starting on Friday, November 15.

PSE&G gas construction update: March 4 week

Posted on March 1, 2024


PSE&G construction map

UPDATE: Due to the weather forecast, PSE&G contractor crews will not work on Main Street on Tuesday, March 5. All traffic lanes will be open. We are waiting for PSE&G to confirm if work will continue on E. High Street.


PSE&G will continue working on the gas pipe replacement project that started in March 2023. All work is weather permitting.

Week of March 4

PSE&G and contractor crews will be working on:

  • E. Main Street, from N. Bridge Street to Park Avenue (completing service appointments). Lane shifts will be used to direct the traffic flow.
  • E. High Street, between Culver Street and N. Gaston Ave

Main Street plan

  • Work on Main Street started at the Bridge Street intersection and will end at Park Avenue
  • Work hours are from 9 am to 3 pm (approved by the state)
  • Crews will start setting up at 8 am and complete breakdown by 4 pm
  • Traffic control will include lane shifts, road closures and detours around work areas, to ensure safety
  • “No Parking” signs will be posted on Main Street, from Division Street to Grove Street
    • “No Parking” hours are from 8 am to 4 pm (to accommodate setup and breakdown)
    • Signs will be moved as the work progresses

Questions

Contact the PSE&G Gas Construction customer hotline at 1-833-661-6400 or email GasWorks@PSEG.com.

Close window