February 15 update: Crews will work on E. Main Street, near Hamilton Street, on Thursday and Friday.
February 14 update: Work was postponed due to inclement weather and will resume on Thursday, February 15.
——————————————–
PSE&G crews will start working on Main Street at 9 am, on Monday, February 12. This work is to connect gas services, and is part of the gas pipe replacement project that started in March 2023.
- Work will start on Main Street, at the Bridge Street intersection
- They will work their way down to Park Avenue
- Work hours are from 9 am to 3 pm (approved by the state)
- Crews will start setting up at 8 am and complete breakdown by 4 pm
- Crews will not work on Saturday, February 17 (due to the weather forecast)
Parking on Main Street
- No parking signs will be posted on Main Street, from Division Street to Grove Street
- No parking hours are from 8 am to 4 pm (to accommodate setup and breakdown)
- Signs will be moved as the work progresses
Traffic Control
Traffic control on Main Street will vary to ensure safety and will include:
- Lane shifts
- Road closures and detours around the work areas, when deemed necessary by Somerville police
Questions
If you have any questions about this project, please contact Mike Halperin at MHalperin@SomervilleNJ.org or call (908) 725-2300 ext. 1958.