Plan for road closures and detours next week, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting.
N. Gaston Ave
Monday, April 22 (8 pm to 6 am)
- There will be a road closure with detours between Union Ave and Main St
- PSEG&G will be installing a gas main
Tuesday, April 23 to Friday, April 26 (9 am to 2:30 pm)
- Expect lane shifts between Union Ave and Main St
- PSEG&G will be connecting service lines
E. Cliff St
- Road will be closed between N Gaston Ave and Eastern Ave
- Work hours: Monday, April 22 to Friday, April 26, from 7 am to 4 pm
- PSE&G will be installing a gas main and connecting service lines
E. High St
- Road will be closed between N Gaston Ave and Eastern Ave
- Work hours: Monday, April 22 to Friday, April 26, from 7 am to 4 pm
- PSE&G will be installing a gas main and connecting service lines