Sunday, November 24: Plan for temporary road closures for the Girls on the Run 5K, starting at 10 am (E. High Street and Grove Street).

News

Category
PSE&G gas construction weekly update

PSE&G gas construction update: week of November 25

Posted on November 22, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, November 25 to Wednesday, November 27 Crews will finish connecting service lines on North Cadillac Dr and Catalina Dr. Crews will not work on Thursday, November 28 or Friday, November 29 (Thanksgiving holiday). View the interactive map to see current work...
PSE&G gas construction weekly update

PSE&G gas construction update: week of November 18

Posted on November 15, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, November 18 to Friday, November 22 Paving and striping is scheduled on Main Street (from N. Gaston Ave to Haynes Street) on Monday, November 18. Working hours will be from 9 am to 5 pm. Detours will be set up on...
PSE&G gas construction weekly update

PSE&G gas construction update: week of November 12

Posted on November 8, 2024

UPDATE: Milling is scheduled on Main Street (from N. Gaston Ave to Haynes Street) on Friday, November 15. Paving and striping is planned on Monday, November 18. Working hours will be from 9 am to 5 pm. Detours will be set up on both days. PSE&G and contractor crews will continue working on the gas...
PSE&G gas construction weekly update

PSE&G gas construction update: week of November 4

Posted on November 1, 2024

PSE&G and contractor crews are connecting service lines, as part of the gas pipe replacement project. Monday, November 4 to Friday, November 8 NOTE: Crews will not be working on Tuesday, November 5, in observance of Election Day. Crews will be scheduling appointments on: Eastern States Pkwy Halsey St Lincoln Ave Roosevelt Pl Schoolhouse Ln...
PSE&G gas construction weekly update

PSE&G gas construction update: week of October 28

Posted on October 25, 2024

PSE&G and contractor crews are connecting service lines, as part of the gas pipe replacement project. Monday, October 28 to Friday, November 1 Crews will schedule appointments on: Cleveland St Eastern States Pkwy Halsey St Roosevelt Pl Schoolhouse Ln View the interactive map to see current work locations. Questions Contact the PSE&G Gas Construction customer...
PSE&G gas construction weekly update

PSE&G gas construction update: week of October 21

Posted on October 17, 2024

PSE&G and contractor crews are connecting service lines, as part of the gas pipe replacement project. Monday, October 21 to Friday, October 25 Crews will schedule appointments on: Cleveland St Halsey St Lincoln Ave Nagle Dr Somer Dr Schoolhouse Ln View the interactive map to see current work locations. Questions Contact the PSE&G Gas Construction...
PSE&G gas construction weekly update

PSE&G gas construction update: week of October 14

Posted on October 10, 2024

PSE&G and contractor crews will be connecting services lines, as part of the gas pipe replacement project. Monday, October 14 to Friday, October 18 Crews will schedule appointments on Fieldstone Dr, Grimm Dr, Nagle Dr, Lincoln Ave and S. Clark Ave. View the interactive map to see current work locations. Questions Contact the PSE&G Gas...
PSE&G gas construction weekly update

PSE&G gas construction update: week of October 7

Posted on October 4, 2024

PSE&G and contractor crews will be connecting services lines, as part of the gas pipe replacement project. Monday, October 7 to Friday, October 11 Crews will schedule appointments on Fieldstone Dr, Grimm Dr, Nagle Dr, Lincoln Ave and S. Clark Ave. View the interactive map to see current work locations. Questions Contact the PSE&G Gas...
PSE&G gas construction weekly update

PSE&G gas construction update: week of September 30

Posted on September 27, 2024

PSE&G and contractor crews will be connecting services lines, as part of the gas pipe replacement project. Monday, September 30 to Friday, October 4 Crews will schedule appointments on Fieldstone Dr, Grimm Dr, Nagle Dr, North Richards Ave, and North and South Clark Ave  View the interactive map to see current work locations. Questions Contact...
PSE&G gas construction weekly update

PSE&G gas construction update: week of September 23

Posted on September 20, 2024

PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. Monday, September 23 to Friday, September 27 Crews will be working to schedule appointments on Fieldstone Dr, Grimm Dr, Nagle Dr, North Richards Ave, and North and South Clark Ave  View the interactive map showing current work locations....
PSE&G gas construction weekly update

PSE&G gas construction update: week of September 16

Posted on September 13, 2024

PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. Monday, September 16 to Friday, September 20 Crews will be working on: Scheduling appointments on Fieldstone Dr, Grimm Dr, Nagle Dr, North and South Richards Ave, and North and South Clark Ave  Crews may also work on S....
PSE&G gas construction weekly update

PSE&G gas construction update: week of September 9

Posted on September 6, 2024

PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. Monday, September 9 to Friday, September 13 Crews will be working on: Scheduling appointments on Fieldstone Dr, Grimm Dr and Nagle Dr, N Richards Ave, S Richards Ave, and  N Clark Ave Scattered tie-in pits in intersections Crews...
PSE&G gas construction weekly update

PSE&G gas construction update: week of September 3

Posted on August 30, 2024

PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. Tuesday, September 3 to Friday, September 6 Crews will be working on: N. Richards Ave Fieldstone Dr Halsey St and Eastern States Pkwy, then moving to Lincoln Ave when finished Crews will also work on S. Adamsville Road...
PSE&G gas construction weekly update

PSE&G gas construction update: week of August 26

Posted on August 23, 2024

PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. Monday, August 26 to Friday, August 30 Crews will be working on: Fieldstone Ave, installing main and connecting services between N Gaston Ave and Schoolhouse Ln Cleveland St, installing main between Union Ave and Halsey St. Continuing onto...
PSE&G gas construction weekly update

PSE&G gas construction update: week of August 19

Posted on August 16, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. All work is weather permitting. Monday, August 19 to Friday, August 23 Crews will be working on: Roosevelt Pl, between Union Ave and Schoolhouse Ln. Continuing onto Lincoln Ave, between Rehill Ave and Cleveland St. Fieldstone Ave, connecting services between N Gaston...
PSE&G gas construction weekly update

PSE&G gas construction update: week of August 12

Posted on August 8, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. All work is weather permitting. Monday, August 12 to Friday, August 16 Crews will be: Installing main on N. Cadillac Dr, between N. Gaston Ave and Riviera Dr. When completed, they will continue to Schoolhouse Ln and Roosevelt Pl, between Union Ave...
PSE&G gas construction weekly update

PSE&G gas construction update: week of August 5

Posted on August 2, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, August 5 to Friday, August 9 All work is weather permitting. Grimm Dr, between Fieldstone Dr and 6 Grimm Dr (Monday) N Cadillac Dr, between N. Gaston Ave and Riviera Dr (Tuesday and Wednesday) Schoolhouse Ln, from N. Gaston Ave to...
PSE&G gas construction weekly update

PSE&G gas construction update: week of July 29

Posted on July 26, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, July 29 to Friday, August 2 All work is weather permitting. Nagle Dr Robin Rd Grimm Dr Connecting services on Rehill Ave, between Union Ave and Fairmont Ave. Follow detour signs. Installing main on N. Richards Ave, between E. Main St...
PSE&G gas construction weekly update

PSE&G gas construction update: week of July 22

Posted on July 19, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, July 22 to Friday, July 26 All work is weather permitting. Installing main on Somer Dr, between N. Gaston Ave and Fieldstone Dr Continuing onto Nagle Dr and Schoolhouse Ln Working on tie-in pits on Codington Pl, along multiple intersections (Monday)...
PSE&G gas construction weekly update

PSE&G gas construction update: week of July 15

Posted on July 11, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, July 15 to Friday, July 19 All work is weather permitting. Fieldstone Dr: Installing a gas main between N. Gaston Ave and Schoolhouse Ln Madison St: Connecting services between Eastern Pkwy and Adamsville Rd S. Richards Ave: Installing a gas main...
Close window