News

Category
PSE&G gas construction weekly update

PSE&G gas construction update: week of March 24

Posted on March 21, 2025

PSE&G crews continue to work on the gas pipe replacement project. Monday, March 24 to Friday, March 28 Hours: 7 am to 3 pm Monday through Wednesday: Connecting new piping to the gas network (tie-in) in scattered locations Thursday and Friday: Digging pits by the hospital at Rehill Avenue, Cleveland Street, and Lincoln Avenue Traffic...
PSE&G gas construction weekly update

PSE&G gas construction update: week of March 17

Posted on March 14, 2025

PSE&G crews continue to work on the gas pipe replacement project. Expect detours and limited parking in sections of Main Street. Pedestrian access to all businesses will be maintained. Monday, March 17 to Friday, March 21 Hours: 7 am to 3 pm Digging pits in scattered locations No work planned on Main Street this week...
PSE&G gas construction weekly update

PSE&G gas construction update: week of March 10

Posted on March 7, 2025

Expect detours and no parking in sections of Main Street, while PSE&G crews work on the gas pipe replacement project. Pedestrian access to all businesses will be maintained. Monday, March 10 to Friday, March 14 Hours: 7 am to 3 pm Main Street (Rt 28), from N. Bridge Street to Maple Street Monday: working in...
PSE&G gas construction weekly update

PSE&G gas construction update: week of March 3

Posted on February 28, 2025

Expect detours and no parking in sections of Main Street, while PSE&G crews work on the gas pipe replacement project. Pedestrian access to all businesses will be maintained. Monday, March 3 to Friday, March 7 PSE&G crews will work from 7 am to 3 pm on Main Street (parking spaces) Scattered locations to tie-in piping to...
PSE&G gas construction weekly update

PSE&G gas construction update: week of February 24

Posted on February 21, 2025

Expect detours and no parking in sections of Main Street, while PSE&G crews work on the gas pipe replacement project. Pedestrian access to all businesses will be maintained. Monday, February 24 to Friday, February 28 The overnight crew will work on Main Street, from N. Bridge St to Maple St, until mid-week (date to be...
PSE&G gas construction weekly update

PSE&G gas construction update: week of February 18

Posted on February 14, 2025

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and "no parking" signs in sections of Main Street. Pedestrian access to all businesses will be maintained. Tuesday, February 18 to Friday, February 21 PSE&G crews will...
PSE&G gas construction weekly update

PSE&G gas construction update: week of February 10

Posted on February 7, 2025

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and "no parking" signs in sections of Main Street. Pedestrian access to all businesses will be maintained. Monday, February 10 to Friday, February 14 The overnight crew...
PSE&G gas construction weekly update

PSE&G gas construction update: week of February 3

Posted on January 31, 2025

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and "no parking" signs in sections of Main Street. Pedestrian access to all businesses will be maintained. Monday, February 3 to Friday, February 7 PSE&G crews are...
PSE&G gas construction weekly update

PSE&G gas construction update: week of January 27

Posted on January 24, 2025

JANUARY 31 UPDATE: PSE&G crews will not work on Main Street tonight, due to weather. ------------------------------------- PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and "no parking" signs in sections of Main Street. Pedestrian access...
PSE&G gas construction weekly update

PSE&G gas construction update: week of January 21

Posted on January 17, 2025

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and "no parking" signs in sections of Main Street. Pedestrian access to all businesses will be maintained. Work Hours 9 am to 2 pm (from January 13...
PSE&G gas construction weekly update

PSE&G gas construction update: week of January 13

Posted on January 10, 2025

PSE&G and contractor crews are now in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April, mainly in the evenings, from 8 pm to 5 am. Expect detours and no parking signs in sections of Main Street. Pedestrian access to all businesses will be...
PSE&G gas construction weekly update

PSE&G gas construction update: week of December 2

Posted on December 2, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, December 2 to Friday, December 6 Connecting service lines on North Cadillac Dr and Schoolhouse Ln Restoring sidewalks and driveway aprons (in scattered locations) View the interactive map to see current work locations. Questions Contact the PSE&G Gas Construction customer hotline...
PSE&G gas construction weekly update

PSE&G gas construction update: week of November 25

Posted on November 22, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, November 25 to Wednesday, November 27 Crews will finish connecting service lines on North Cadillac Dr and Catalina Dr. Crews will not work on Thursday, November 28 or Friday, November 29 (Thanksgiving holiday). View the interactive map to see current work...
PSE&G gas construction weekly update

PSE&G gas construction update: week of November 18

Posted on November 15, 2024

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, November 18 to Friday, November 22 Paving and striping is scheduled on Main Street (from N. Gaston Ave to Haynes Street) on Monday, November 18. Working hours will be from 9 am to 5 pm. Detours will be set up on...
PSE&G gas construction weekly update

PSE&G gas construction update: week of November 12

Posted on November 8, 2024

UPDATE: Milling is scheduled on Main Street (from N. Gaston Ave to Haynes Street) on Friday, November 15. Paving and striping is planned on Monday, November 18. Working hours will be from 9 am to 5 pm. Detours will be set up on both days. PSE&G and contractor crews will continue working on the gas...
PSE&G gas construction weekly update

PSE&G gas construction update: week of November 4

Posted on November 1, 2024

PSE&G and contractor crews are connecting service lines, as part of the gas pipe replacement project. Monday, November 4 to Friday, November 8 NOTE: Crews will not be working on Tuesday, November 5, in observance of Election Day. Crews will be scheduling appointments on: Eastern States Pkwy Halsey St Lincoln Ave Roosevelt Pl Schoolhouse Ln...
PSE&G gas construction weekly update

PSE&G gas construction update: week of October 28

Posted on October 25, 2024

PSE&G and contractor crews are connecting service lines, as part of the gas pipe replacement project. Monday, October 28 to Friday, November 1 Crews will schedule appointments on: Cleveland St Eastern States Pkwy Halsey St Roosevelt Pl Schoolhouse Ln View the interactive map to see current work locations. Questions Contact the PSE&G Gas Construction customer...
PSE&G gas construction weekly update

PSE&G gas construction update: week of October 21

Posted on October 17, 2024

PSE&G and contractor crews are connecting service lines, as part of the gas pipe replacement project. Monday, October 21 to Friday, October 25 Crews will schedule appointments on: Cleveland St Halsey St Lincoln Ave Nagle Dr Somer Dr Schoolhouse Ln View the interactive map to see current work locations. Questions Contact the PSE&G Gas Construction...
PSE&G gas construction weekly update

PSE&G gas construction update: week of October 14

Posted on October 10, 2024

PSE&G and contractor crews will be connecting services lines, as part of the gas pipe replacement project. Monday, October 14 to Friday, October 18 Crews will schedule appointments on Fieldstone Dr, Grimm Dr, Nagle Dr, Lincoln Ave and S. Clark Ave. View the interactive map to see current work locations. Questions Contact the PSE&G Gas...
PSE&G gas construction weekly update

PSE&G gas construction update: week of October 7

Posted on October 4, 2024

PSE&G and contractor crews will be connecting services lines, as part of the gas pipe replacement project. Monday, October 7 to Friday, October 11 Crews will schedule appointments on Fieldstone Dr, Grimm Dr, Nagle Dr, Lincoln Ave and S. Clark Ave. View the interactive map to see current work locations. Questions Contact the PSE&G Gas...
Close window