Saturday, March 22: Green Street will be closed between Davenport Street and Mercer Street, from 10 am to 4 pm, for the grand reopening of Shiloh Pentecostal Church.

Category: PSE&G gas construction updates

PSE&G gas construction update: February 26 week

February 27 update: PSE&G crews will not work on Wednesday, February 28, due to the weather forecast. All lanes will be open on Main Street and parking will be permitted until work resumes on Thursday, February 29. ——————————————————————————————– PSE&G will continue working on the gas pipe replacement project that started in March 2023. Week of … Continued

PSE&G gas construction update: February 20

2/22 Update: PSE&G will not work on Main Street on Friday, February 23. This change is due to the weather forecast. ———————————————————————————————————— Main Street Update: PSE&G will be connecting services on Main Street, from N. Bridge Street to Grove Street, on February 22 and 23. Traffic will shift over in both directions to allow work … Continued

PSE&G gas construction update: February 14

February 15 update: Crews will work on E. Main Street, near Hamilton Street, on Thursday and Friday. February 14 update: Work was postponed due to inclement weather and will resume on Thursday, February 15. ——————————————– PSE&G crews will start working on Main Street at 9 am, on Monday, February 12. This work is to connect … Continued

PSE&G gas construction update: December 18

PSE&G and contractor crews are working in Somerville to replace gas mains and services. Monday, December 18 to Friday, December 22 E. Cliff  St (between Culver St and N. Gaston Ave): Installing main and connecting services Culver St (between E High St and E Cliff St): Installing main and connecting services Note: PSE&G picked up … Continued

PSE&G gas construction update: December 11

PSE&G and contractor crews are working in Somerville to replace gas mains and services. Monday, December 11 to Friday, December 15 E. Cliff  St (between Culver St and N. Gaston Ave): Installing main and connecting services Culver St (between E High St and E Cliff St): Installing main and connecting services About this project This … Continued

PSE&G gas construction update: December 4

PSE&G is working in Somerville to replace gas mains and services. Monday, December 4 to Friday, December 8 E. Cliff  St (between Culver St and N. Gaston Ave): Installing main and connecting services Culver St (between E High St and E Cliff St): Installing main and connecting services About this project This work is Phase … Continued

PSE&G gas construction update: November 20

Monday, November 20 to Wednesday, November 22 E. Cliff St (between Culver St and N. Gaston Ave): Installing main and connecting services Culver St (between Bartine St and E. Cliff St): Installing main and connecting services Additional Locations: PSEG will notify Somerville Police as the week progresses We do not expect crews to work on November … Continued

PSE&G gas construction update: November 13

Main St update: PSE&G will not work overnight on Thursday, November 16. They will work overnight on Friday, November 17, starting at about 7 pm. Plan for lane shifts and no parking from Maple St to Grove St. This is the last day for night work until January. Monday, November 13 to Saturday, November 18 Main … Continued

PSE&G Gas Construction Update: November 6

PSE&G is planning to add more locations this week. They will notify Somerville Police who will redirect traffic, as needed. Monday, November 6 to Saturday, November 11 Main Street (N. Bridge St intersection): OVERNIGHT on Wednesday and Thursday. Lane shifts (Maple St to Grove St), from 8 pm to 5 am, with traffic control setting … Continued

PSE&G Gas Construction Update: October 30

PSE&G is working in Somerville to replace gas mains and services. This work is Phase 1 of a 10-12 month gas construction project. All crews will first finish installing new mains and then proceed to connect service lines. Expect an increase in traffic, loud noise, and presence of heavy equipment and machinery in these areas. All … Continued