The Recreation office is closed from July 26 to August 5. The Fire Prevention department will be closed from July 29 until August 5. The Vital Statistics office will be closed for lunch (1 to 2 pm), from August 1 to August 9.

Category: PSE&G gas construction updates

No parking during PSE&G road construction

May 23 Update: PSE&G has completed this phase of the paving project. They will start striping the roads on Friday, May 24 and continue into early the following week. PSE&G started restoring Somerville roads with permanent paving on Monday, May 13. We will update this schedule as PSE&G provides new information. Last Update: May 23, … Continued

PSE&G gas construction update: week of May 20

PSE&G and contractor crews will continue working on the gas pipe replacement project. All work is weather permitting. Monday, May 20 to Friday, May 24 N. Gaston Avenue Crews will be connecting services between Union Ave and Main St. Work hours are from 9 am to 2:30 pm Traffic control will include lane shifts and … Continued

PSE&G gas construction update: May 13 week

PSE&G and contractor crews will continue working on the gas pipe replacement project. All work is weather permitting. Monday, May 13 to Friday, May 17 N. Gaston Avenue Crews will be connecting services between Union Ave and Main St. Work hours are from 9 am to 2 pm Traffic control will include lane shifts and … Continued

PSE&G gas construction update: May 6 week

Plan for road closures and detours, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. N. Gaston Avenue Monday, May 6 to Friday, May 10 Crews will be connecting services between Union Ave and Main St. Work hours are from 9 am to 2 pm Traffic … Continued

PSE&G gas construction update: April 29 week

Plan for road closures and detours next week, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. Reimer Street Monday, April 29 to Wednesday, May 1 Crews will be connecting services between N. Gaston Ave and Eastern Ave Work hours are from 9 am to 2 … Continued

PSE&G gas construction update: April 22 week

Plan for road closures and detours next week, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. N. Gaston Ave Monday, April 22 (8 pm to 6 am) There will be a road closure with detours between Union Ave and Main St PSEG&G will be installing … Continued

PSE&G gas construction update: April 15 week

Plan for road closures and detours next week, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. N. Gaston Ave There will be a road closure with detours between Union Ave and Main St Work hours: Monday, April 15 to Thursday, April 18, from 8 pm … Continued

PSE&G gas construction update: April 8 week

Plan for road closures and detours next week, as PSE&G and contractor crews continue working on the gas pipe replacement project. All work is weather permitting. N. Gaston Ave There will be a lane shift with detours between Union Ave and Main St Work hours are from 8 pm to 6 am PSEG&G will be … Continued

PSE&G gas construction update: March 25 week

Plan for road closures in sections of Reimer St, Eastern Ave, E Cliff St, and E High St next week, as PSE&G continues working on the gas pipe replacement project. All work is weather permitting. Reimer Street Monday, March 25 and Tuesday, March 26 Road will be closed between Vanderveer Ave and N. Gaston Ave, … Continued

PSE&G gas construction update: March 18 week

PSE&G is completing post-construction restoration work for the gas pipe replacement project that started in March 2023. All work is weather permitting. Traffic impact This work does not include road closures, but parking will be restricted in active work areas. Please pay attention to posted signs. Crews will be working on: 2nd St 3rd St Brookside … Continued

Close window