Category: PSE&G gas construction updates

PSE&G gas construction update: week of February 3

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and “no parking” signs in sections of Main Street. Pedestrian access to all businesses will be maintained. Monday, February 3 to Friday, February 7 PSE&G crews are … Continued

PSE&G gas construction update: week of January 27

JANUARY 31 UPDATE: PSE&G crews will not work on Main Street tonight, due to weather. ————————————- PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and “no parking” signs in sections of Main Street. Pedestrian access … Continued

PSE&G gas construction update: week of January 21

PSE&G and contractor crews are in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April. Expect detours and “no parking” signs in sections of Main Street. Pedestrian access to all businesses will be maintained. Work Hours 9 am to 2 pm (from January 13 … Continued

PSE&G gas construction update: week of January 13

PSE&G and contractor crews are now in the final phase of the gas pipe replacement project. Crews will be working on Main Street from January through April, mainly in the evenings, from 8 pm to 5 am. Expect detours and no parking signs in sections of Main Street. Pedestrian access to all businesses will be … Continued

PSE&G gas construction update: week of December 2

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, December 2 to Friday, December 6 Connecting service lines on North Cadillac Dr and Schoolhouse Ln Restoring sidewalks and driveway aprons (in scattered locations) View the interactive map to see current work locations. Questions Contact the PSE&G Gas Construction customer hotline … Continued

PSE&G gas construction update: week of November 25

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, November 25 to Wednesday, November 27 Crews will finish connecting service lines on North Cadillac Dr and Catalina Dr. Crews will not work on Thursday, November 28 or Friday, November 29 (Thanksgiving holiday). View the interactive map to see current work … Continued

PSE&G gas construction update: week of November 18

PSE&G and contractor crews will continue working on the gas pipe replacement project. Monday, November 18 to Friday, November 22 Paving and striping is scheduled on Main Street (from N. Gaston Ave to Haynes Street) on Monday, November 18. Working hours will be from 9 am to 5 pm. Detours will be set up on … Continued

PSE&G gas construction update: week of November 12

UPDATE: Milling is scheduled on Main Street (from N. Gaston Ave to Haynes Street) on Friday, November 15. Paving and striping is planned on Monday, November 18. Working hours will be from 9 am to 5 pm. Detours will be set up on both days. PSE&G and contractor crews will continue working on the gas … Continued

PSE&G gas construction update: week of November 4

PSE&G and contractor crews are connecting service lines, as part of the gas pipe replacement project. Monday, November 4 to Friday, November 8 NOTE: Crews will not be working on Tuesday, November 5, in observance of Election Day. Crews will be scheduling appointments on: Eastern States Pkwy Halsey St Lincoln Ave Roosevelt Pl Schoolhouse Ln … Continued

PSE&G gas construction update: week of October 28

PSE&G and contractor crews are connecting service lines, as part of the gas pipe replacement project. Monday, October 28 to Friday, November 1 Crews will schedule appointments on: Cleveland St Eastern States Pkwy Halsey St Roosevelt Pl Schoolhouse Ln View the interactive map to see current work locations. Questions Contact the PSE&G Gas Construction customer … Continued

Close window